HOTSPOT
Answer the following question about Schein’s concept of survival and learning anxieties.
Column 1 is a list of messages about the change given to Sales staff. For each message in Column 1, select from Column 2 the appropriate element of Schein’s concept of survival and learning anxieties. Each selection from Column 2 can be used once, more than once or not at all.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Which item is MOST likely to be considered as a pain point for a ‘Sales team member’ stakeholder?
- A . Rebranding gives the company a modern look that has been missing historically.
- B . Comprehensive training is required to broaden skills, that are recognized as best practice.
- C . Increased effort will be needed initially to learn the new supporting business processes.
- D . This gives an opportunity for all staff to be involved and engaged in shaping the change.
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?
- A . Encourage the Marketing Director to attend the End of Timebox Review.
- B . Attend the next Daily Stand-up to raise an issue about the windows.
- C . Prepare a summary of progress against plan, for presentation at the review.
- D . Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.