Which of the following are suitable scenarios to use Jira group? (Choose four.)
- A . Members of the group are responsible for making bulk changes on multiple issues.
- B . The project administrator will manage group membership.
- C . Same users will be working on multiple projects.
- D . Permission can be managed at the global level.
- E . The site administrator will manage group membership.
- F . Team members require ‘Work On Issues’ permission to log work done.
Dom created an issue in Project A. Now he wants to move the issue to Project B.
According to the information below, which of the following fields will retain their values after moving the issue to Project B? (Choose two.)
Project A custom fields:
– Custom Field A – Text Field (single line)
– Custom Field B – Text Field (single line)
– Custom Field C – Version picker
Project B custom fields:
– Custom Field A – Text Field (single line)
– Custom Field C – Version picker
- A . Custom Field A
- B . Components
- C . Fix Versions
- D . Labels
- E . Custom Field C
- F . Custom Field B
Sarah is working on a financial project that involves sensitive information which should not be openly available to any users. She wants to create a new team-managed project for her assignment.
Suggest the best access level for Sarah’s project.
Note:
– Company-managed projects are formerly known as classic projects.
– Team-managed projects are formerly known as next-gen projects.
- A . Limited
- B . Individual
- C . Private
- D . Open
- E . Restricted
- F . Public
Razi has added and enabled the automation below. After Razi creates an issue, which of the following are true about the assignee of that issue? (Choose two.)
(Assume this automation is using the default priority, and all of the required permissions and labels exist.)
- A . Issues with the highest priority and a Java label will be assigned to Unassigned.
- B . Issues with the highest priority will be assigned to Nina.
- C . Issues with a high priority will be assigned to Razi.
- D . Issues with a high priority will be assigned to Nina.
- E . Issues with a high priority will be assigned to Unassigned.
- F . Issues with a Java label will be assigned to Razi.
According to the components below, who will be the assignee if a user created a ticket with all components?
Project lead: Razi
Project default assignee: Unassigned
- A . Nina
- B . Razi
- C . Nick
- D . Unassigned
- E . Dom
Razi’s team just completed their first sprint.
What can they learn from this chart? (Choose three.)
(Assume Remaining Estimate and Time Spent is disabled for this board.) This sprint ends with 0 story points.
- A . There are 2 issues resolved on July 8th.
- B . Some of the issues are still unresolved.
- C . This sprint starts with 20 story points.
- D . Some of the issues are resolved during non-working days.
- E . There are no scope changes in this sprint.
A Jira workflow contains 3 statuses; To Do, In Progress, and Done.
Which of the following JQL will return issues that have never been in ‘Done’ status?
- A . resolution != null
- B . status was not Done
- C . resolution is EMPTY
- D . status != Done
- E . status was in ("To Do", "In Progress")
Nina found that the roadmap no longer appears on her board.
Which of the following is the possible cause for this problem?
Note:
– Company-managed projects are formerly known as classic projects.
– Team-managed projects are formerly known as next-gen projects.
- A . Roadmap is disabled by the site administrator.
- B . There is no Epic created in the project.
- C . Nina does not have ‘View Read-Only Workflow’ permission.
- D . Board Filters contains multiple projects.
- E . Nina is using a team-managed project. Roadmap only exists in company-managed Jira projects.
Razi is the Jira administrator for the WINDOWS Jira project. He received a new request to create a new Jira project called LINUX, and both projects need to have the same configurations.
Razi created the LINUX Jira project using the shared configuration option to ensure both projects have the same configurations.
Assuming the WINDOWS project is already configured with all of the below configurations, which configurations does Razi have to update in the LINUX project manually? (Choose three.)
- A . Status
- B . Project Avatar
- C . Version
- D . Priority
- E . Notification
- F . Components
Which of the following is false about creating boards?
- A . Users can create a new board from existing Jira projects.
- B . Users can create a new board from the existing Saved Filter.
- C . Users cannot create a board with multiple projects, but they can add more projects once they create the board.