Which JQL query can users use to get a list of issues in the current sprint for the "Udemy" project?
- A . project = "Udemy" AND Sprint in openSprints()
- B . project = "Udemy" AND Sprint in activeSprint()
- C . project = "Udemy" AND Sprint = activeSprint()
- D . project = "Udemy" AND Sprint = openSprints()
Sarah’s Team is responsible for developing a web application for their client. The modules will be delivered to the client batch by batch every two weeks.
Which of the following Jira Software template is suitable for Sarah’s Team?
- A . Kanban
- B . IT service management
- C . Project management
- D . Scrum
- E . Bug Tracking
Users created a new custom field called Environment that has two values:
– Production
– Non-Production.
They need a table report to group issues from Production and Non-Production, and the overall status of those issues. The report should return a table containing three groups; issues with Production value, issues with Non-production value, and issues with a null value.
Which report is suitable for this use case?
- A . Time Since Issues Report
- B . Average Age Report
- C . Single Level Group By Report
- D . Resolution Time Report
- E . Pie Chart Report
- F . Time Tracking Report
Which of the following are suitable use-cases to use issue-level security? (Choose two.)
- A . Only managers can view certain projects.
- B . Only managers can view and edit high-priority issues.
- C . Only managers can view the development panel.
- D . Only managers can view issues created by the manager level.
- E . Only managers can move issues to other projects.
Which of the following are false about the roadmap? (Choose three.)
- A . Users can choose which epics they want to display on the dashboard. Either Complete or Incomplete.
- B . Users can change the view setting to customize their roadmap’s view. The changes will apply to all users that have access to that project.
- C . Schedule bars for child issues are currently available for scrum teams only.
- D . Users can customize epic’s color directly from the roadmap.
- E . Users can change the epic bar timeline to weeks, months, quarters, or yearly.
__________ listen to any events selected by users to start their automation rules.
- A . Conditions
- B . Listeners
- C . Triggers
- D . Steps
- E . Requirements
- F . Actions
Sarah created a new custom field called ‘Project Cost’. She cannot view the field in some of the issues.
Which of the following is true?
- A . ‘Project Cost’ value is empty.
- B . ‘Project Cost’ is one of the ‘Hidden fields’.
- C . She needs ‘Browse Projects’ permission.
- D . Some issues have ‘Issue Level Security’ applied.
Which of the following can be explained from the chart below?
- A . Users have not started the sprint yet.
- B . Users deleted the sprint.
- C . Users closed some issues the moment the sprint started.
- D . There are no issues in the sprint.
Which of the following are true about labels? (Choose four.)
- A . Labels are unreliable for searching issues.
- B . Labels can only be accessed at the project level.
- C . Users cannot use labels in the report.
- D . Users can use the ‘Bulk Change’ tool to change labels’ values.
- E . Only project administrators can create new labels.
- F . Labels might contain inconsistent values.
Which of the following indicates that the productivity of the team is increasing in Control Chart report? (Choose two.)
- A . Rolling average line showing a downtrend.
- B . More issues or a group of issues are below the average line.
- C . Rolling average line showing an uptrend.
- D . Rolling average line is consistently close to the average line.
- E . More issues or a group of issues are above the average line.