After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window.
Which of the following should be added to the issue log?
- A . Continuous integration
- B . Rollback plan
- C . Customer notification
- D . Automated testing
A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year.
Which of the following actions would the PM most likely perform?
- A . Call the previous PM for advice on risks and issues.
- B . Ask the project sponsor to provide previous final project report results.
- C . Complete the project charter using the other PM’s subject matter expertise.
- D . Use existing artifacts and accommodate based on the current project success criteria.
Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
- A . Dashboard
- B . Status report
- C . Meeting minutes
- D . Communication plan
A project team is defining operational training, discussing a go-live date, and describing the operational handoff.
Which of the following best describes what the team is developing?
- A . The project closeout report
- B . A handover to operations
- C . Phase-gate review documentation
- D . A transition plan
While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project.
Which of the following should the PM do FIRST?
- A . Escalate the finding to the change control board.
- B . Add a risk to the risk register for validation.
- C . Consult the RACI matrix to identify ownership of the risk.
- D . Have a meeting with the project sponsor and main stakeholders.
SIMULATION
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
• Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
Which of the following best describes a manufacturer’s obligation to repair or change, without extra costs, any part of a product that is not functioning?
- A . Service-level agreement
- B . Functional testing
- C . Warranty period
- D . Audit
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project.
Which of the following activities still needs to be performed to complete the schedule?
- A . Allocate resources.
- B . Determine the project budget
- C . Develop a communication plan.
- D . Establish baselines.
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project’s closure.
Which of the following would have most likely prevented the data from being stolen?
- A . Removing access
- B . Closing contracts
- C . Project sign-off
- D . Project evaluation
A project sponsor asked the PM to provide a summary of the current financial status.
The PM uses the following burn up chart for the analysis:
Based on the chart, which of the following is the current status of the project?
- A . Behind schedule and over budget
- B . Behind schedule and under budget
- C . Ahead of schedule and over budget
- D . Ahead of schedule and under budget