A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.
The production planner increases the lead time of an item. On the next master planning output, the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.
The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.
You need to resolve the issue.
What should you do?
- A . Increase positive days.
- B . Decrease positive days.
- C . Decrease negative days to be less than the item lead time.
- D . Increase negative days to be greater than the item lead time.
You are the lead product design engineer at a plastics manufacturing company.
You implement a new process that uses a single tool to produce three finished goods at the same time.
You need to set up the planning item number and formula to correctly to manufacture the three items.
Which three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
- A . Create item number for planning item and the associated formula.
- B . Specify each of the finished good items as co-products.
- C . Add minimum and maximum quantities on formula.
- D . Assign co-products to the formula.
- E . Add a coverage group to the formula.
DRAG DROP
A company uses the asset management module in Dynamics 365 Supply Chain Management.
A machine on the shop floor is noisy and emitting an odd smell. The shop floor manager must alert the repair team that the asset might require a repair, or a series of repairs, by one or more specialized repair technicians. All repair records must tie back to the initial investigation record in case of a safety audit.
You need to create components to initiate the process of tracking the requests.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
You are the lead product design manager at a Process manufacturing plant.
A formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be used in other production batches.
You need to select the by-product cost allocation.
Which cost allocation type should you use?
- A . Per series
- B . Percent
- C . Recycled
- D . Per quantity
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A client subcontracts production work to a vendor for production operations.
You need to model subcontracting of route operations in production orders.
Solution: Ensure that material routing process is independent of the services procurement process.
Does the solution meet the goal?
- A . Yes
- B . No
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing company produces electronic components and devices.
The company has scheduling issues related to using working time calendars in manufacturing.
You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.
Solution: Enable route groups for a capacity job type.
Does the solution meet the goal?
- A . Yes
- B . No
A company uses engineering change management in Dynamics 365 Supply Chain Management. The Product readiness checks feature is turned off.
An existing engineering product must be reconfigured for a new product readiness policy.
You need to change the product readiness policy.
Where should you make this change?
- A . default order settings
- B . shared product
- C . engineering category
- D . product configuration model
- E . released product
A beverage company uses Dynamics 365 Supply Chain Management batch processing for production.
You need to identify the ingredient type used in batch processing when the base attribute of a product is added to a formula line.
What is the ingredient type?
- A . active
- B . compensating
- C . filler
- D . none
A company plans to use master planning in Dynamics 365 Supply Chain Management. The company will sell items between legal entities.
The company has several facilities across legal entities that can manufacture the same products. Same products are produced only in some plants. To meet product demand, when one facility is over capacity, another facility is used to fulfill the downstream demand.
The organizational entities are:
• LegalEntityA: Plant 1.2, and 3
• LegalEntityB: Plant4and 5
• LegalEntityC: Plant 6. 7, and 8
The following plants must be planned together:
• Plant 1. Plant 3. and Plant 4
• Plant 2. Plant 6. and Plant 8
• Plant 5 and Plant 7
You need to configure master planning for the facilities.
Which configuration mechanism should you use?
- A . Production groups
- B . Item model groups
- C . Coverage groups
- D . Intercompany planning groups
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing company has a new speaker that is available with standard and premium carbon fiber options.
For the premium option, speakers are made to order. Customers can choose from seven product attributes at different prices.
You need to create and configure the product and pricing for the new speaker.
Solution: Create a constraint-based product with configurations. Use a price model to calculate the different configurable option costs.
Does the solution meet the goal?
- A . Yes
- B . No