Question #1
(Select 2) What are the responsibilities of a Business Owner?
- A . Assign business value to Team Objectives during PI Planning.
- B . Participate in Post-PI Planning and assist trains in adjusting ART PI plans as needed.
- C . Assign business value to Epics and Features.
- D . Ensure that the Solution Demo occurs.
- E . Determine the product Roadmap
Question #2
Multiple ARTs in a Value Stream typically require coordination at the Value Stream Level.
- A . True
- B . False
Question #3
What are the ways to evolve the Solution Intent from variable to fixed scope? (Select 2)
- A . Creating work breakdown structures.
- B . Modeling
- C . Adapting WIP limits
- D . Building prototypes
Question #4
(Select 2) Why is Architectural Runway important?
- A . It supports a stable velocity.
- B . It provides the documentation on which Features and Capabilities are built.
- C . It iteratively evolves the architecture to meet changing needs.
- D . It allows for nontechnical changes
Question #5
What is Cost of Delay?
- A . Cost incurred when system integration appears too late in the PI.
- B . Opportunity cost and deferred revenue.
- C . Penalty for nonperformance.
- D . Cost of not addressing risk early on.
Question #6
Leader as expert and leader as conductor can be appropriate leadership models.
- A . True
- B . False
Question #7
What are the 3 primary outputs of PI Planning? (select 3)
- A . Program board
- B . Team PI Objectives
- C . Top 10 Features
- D . Vote of confidence/commitment
- E . Portfolio Vision
- F . Iteration Goals
Question #8
What is the key reason for deploying each team increment to the production-equivalent staging environment?
- A . Teams can verify whether new functionality or Nonfunctional Requirements are compatible with the current production configuration.
- B . It allows the System Team to test the deployability of the Solution.
- C . It enable SAFe teams to Develop on Cadence and Release Any Time.
- D . If something goes wrong with the production environment, teams can switch their staging to perform the role of production.
Question #9
What activity does NOT happen on Day 1 of PI Planning? (Select 2)
- A . ROAMing of risks.
- B . Assignment of business value.
- C . Management review and problem-solving meeting.
- D . Team breakouts.
- E . Hourly checkpoints.