True or False: Professional Scrum with Kanban can be used without Work in Progress (WIP) Limits. (choose the best answer)
- A . True. Physical Kanban boards can be used as an alternative to WIP Limits as it will improve visualization and enhance communication.
- B . False. Professional Scrum with Kanban cannot be used without explicit WIP Limits.
- C . True. A strong team identity using Squads and tribes can be a valid alternative to WIP Limits.
- D . False. WIP Limits are crucial to conducting Daily Stand Up meetings that control not having too much work.
Which one of the following concepts does the Just-In-Time (JIT) method advocate? (choose the best answer)
- A . Upstream processes run simultaneously with downstream processes.
- B . Processes are triggered by a pull request based on demand.
- C . Processes are initiated by a push request based on requirements.
- D . The use of requirement planning to the maximum resource capacity.
True or False: Cycle Time is used as a leading indicator to determine the length of a certain Product Backlog Item’s feedback loop. Choose only ONE best answer.
B. TRUE
C. FALSE
Which of the following Scrum artifacts is a form of the Work in Progress (WIP) Limit? (choose the best answer)
- A . The Product Backlog.
- B . There is no such component in the Scrum framework.
- C . The Sprint Backlog.
- D . The Burn-down chart.
- E . Definition of "Done".
- F . The Sprint Goal.
True or False: When using Scrum with Kanban you can release multiple times during the Sprint.
- A . True
- B . False
What are the benefits of having early, frequent, and consistent feedback loops? (choose the best answer)
- A . Increased customer satisfaction.
- B . Improved workflows.
- C . Identifying and addressing problems early.
- D . All of the above.
True or False: Reduced productivity is the result of optimizing WIP limits.
- A . TRUE
- B . FALSE
Only a Product Owner and Developers are the needed when applying Kanban in Scrum.
- A . TRUE
- B . FALSE
True or False: A leading indicator for the length of the feedback loop, for an in progress item, can be its Work Item Age.
- A . TRUE
- B . FALSE
True or False: The Scrum Team’s aim for predictable cycle time can seen by the Service Level Expectations (SLE) that they set to themselves.
- A . TRUE
- B . FALSE