Which statement best describes the Sprint Backlog as the output of the Sprint Planning? (Choose the best answer)
- A . Every item has a designated owner.
- B . It is ordered by the Product Owner.
- C . Each task is estimated in hours.
- D . It is the Developers plan for the Sprint.
- E . It is a complete list of all work to be done in a Sprint.
The Daily Scrum is an event that happens every day.
What would be three key concerns if the frequency were to be lowered to every two or three days? (choose the best three answers)
- A . Too much work is spent updating the Scrum board before the meeting,
- B . The Product Owner cannot accurately report progress to the stakeholders.
- C . Opportunities to inspect and adapt the Sprint Backlog are lost.
- D . The Sprint Backlog may become inaccurate,
- E . Impediments are raised and resolved more slowly.
- F . The Scrum Master loses the ability to update the Gantt chart properly.
In accordance with Scrum theory, how should a group of 100 people be divided into multiple Scrum Teams? (Choose the best answer)
- A . It does not really matter since you can rotate the teams every Sprint to spread knowledge.
- B . Create a matrix of skills, seniority, and level of experience to assign people to teams.
- C . Check with the allocation department to see who has worked together before and make these the first teams.
- D . Understanding the product, the product vision and the rules of the Scrum framework, the people divide themselves into teams.
What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning? (Choose the best answer)
- A . Sprint Planning is canceled so refinement can be done first.
- B . The Scrum Master should not allow this to happen. Look for a new Scrum Master and re-start the Sprint.
- C . Nothing in particular.
- D . The Product Owner should select the Sprint Goal for the Scrum Team so that work can begin
- E . The Developers will find it difficult to create a Sprint forecast they are confident they can meet.
Which metrics will help a Product Owner determine if a product is delivering value? (Choose the best two answers)
- A . Productivity.
- B . Time to market.
- C . Velocity.
- D . Percentage of scope implemented.
- E . Customer satisfaction
Which statement best describes a Product Owner’s responsibility? (choose the best answer)
- A . Keep stakeholders from distracting the Developers.
- B . Ensuring that the work meets the commitments to the stakeholders.
- C . Directing the Developers.
- D . Maximizing the value of the work the Scrum Team does.
Which outcome is expected as a Scrum Team matures? (choose the best answer)
- A . There will be no need for a time boxed Sprint.
- B . They will improve their Definition of Done to include more stringent criteria.
- C . The Sprint Retrospectives will grow to be longer than 4 hours.
- D . A Scrum Master is no longer needed since they are a mature team now.
- E . Sprint Reviews will no longer be needed.
Which of the following practices might help the Product Owner minimize waste in developing and sustaining the Product Backlog? (Choose the best two answers)
- A . Avoid distracting the Scrum Team by maintaining newly gathered Product Backlog items in a separate Product Backlog until they are fully understood.
- B . Remove items from the Product Backlog that have not been addressed in a longtime.
- C . Hand off ownership of the Product Backlog to someone else.
- D . Only fully describe Product Backlog items when it seems likely they will be implemented.
A Product Owner is accountable for maximizing the value of the product that is the result of the Work of the Scrum Team.
Which of the following can be delegated to others, while the Product Owner remains accountable for the work? (Choose the best two answers)
- A . Attending the Sprint Retrospective
- B . Attending the Sprint Review.
- C . Ordering Product Backlog items.
- D . Developing and communicating the Product Goal.
Which is NOT a valid consideration when ordering a Product Backlog? (Choose the best answer)
- A . Importance to customers.
- B . Tools and techniques,
- C . Alignment with business strategy and goals.
- D . Risk.
- E . Dependencies on other Product Backlog items.